RSS Feed

Monthly Archives: December 2013

Ostrander Wind Developer Says Gates will Protect Turtles

From the Wellington Times

by Rick Conroy

The developer seeking to construct nine 50-storey industrial wind turbines at
Ostrander Point is now proposing to erect a series of gates on provincially
owned crown land—in a last ditch maneuver to persuade a provincial court to
overturn an Environmental Review Tribunal decision that took away the
developer’s permit to build the project in a landmark ruling issued earlier
this year.

LANDMARK DECISION

In July, after more than 40 days of hearings, the Tribunal revoked a Ministry
of Environment approval of the project in which Gilead Power Corporation
proposed to develop a nine-turbine wind project on Crown land on the shores of
South Marysburgh. The two member panel ruled that the project would cause
serious and irreversible harm to the Blanding’s turtles that reside in this
rare alvar habitat at Ostrander Point. The Tribunal concluded, too, that
measures proposed by the developer to lessen the impact of the development on the
turtles were untested and unlikely to be effective. Given that the Blanding’s
turtle is an endangered species, they decided the potential harm was too great,
and once inflicted could not be undone.

It was a precedent-setting decision— not since the provincial government had
enacted legislation to reduce the administrative and regulatory hurdles for
wind and solar energy developers had an environmental review tribunal revoked
an approval permit. Conservation groups and environmentalists rejoiced— as did
everyone else opposed to Ontario’s natural heritage being spoiled by 500-foot
towers of carbon and steel structures.

The developer appealed the Tribunal decision, along with the Ministry of
Environment, seeking to uphold the approval of the project.

THE APPEAL

Among other things, the developer and the MOE will argue that the Tribunal
exceeded its jurisdiction. They will argue that the Ministry of Natural
Resources had given the developer the ability to “kill, harm or harass” the
endangered species. And that the Tribunal lacked the authority to second guess
the provincial ministry.

Gilead Power has a lot riding on the appeal, scheduled to be heard in January
in Toronto. It is clearly not willing to risk the outcome of this project on
jurisdictional interpretation. Instead it is seeking to take away the issue
raised by the Tribunal— specifically the well-being of the creatures at the
centre of the Tribunal’s decision—the Blanding’s turtle. Once again, it has the
Ministry of Natural Resources on its side.

On January 20 the developer will seek to present new evidence to the appeal
hearing. Specifically it will ask the court to consider a plan to erect a
series of gates securing access to the road network it wants to build on Crown
land at Ostrander Point.

“Restricting public access to the access roads would also provide enhanced
protection for wildlife, including species at risk, from traffic mortality,”
wrote Mike Lord to the Ontario Ministry of Resources (MNR) in August.

In September a MNR official agreed it would issue a lease of the Crown land to
the developer to enable it to build the fence, pending the approval of the
project. The MNR also sought a “Project Access and Control Plan” for the access
roads. That plan calls for six double swing gates to be erected at key points,
one at the entrance and at five other locations where pre-existing trails
intersect with the proposed access road. The gates would be locked from May 1
to October 15. Gilead staff will monitor and enforce access restrictions.

Gilead staff will report monthly on issues of public motor vehicles bypassing
the gates.

Quoting from the Gilead access control plan: “Project staff will be trained on
how to answer questions from the public regarding the need for gated access on
the Project access roads.”

In its motion the developer will argue that it has taken these steps in order
to resolve the Tribunal’s “stated concern”. They will argue the Tribunal should
have given it the opportunity to address the issue, rather than revoke the
permit. And, that the provincial court should consider this new evidence to
satisfy “natural justice.”

Myrna Wood says the developer and the MOE have come far too late in the process
to present new evidence. Worse, she says, the developer and the MNR struck this
deal with MNR behind closed doors—without any public consultation about this
use of Crown Land.

She argues, too, that a few gates will not eliminate the threat the project
poses to the Blanding’s turtle’s habitat.

“Gilead’s emphasis on road mortality is an attempt to avoid the Tribunal’s main
concern, said Wood. “that is, the destruction of the whole habitat.”

Upping the ante, the developer has also asked the court to make the Prince
Edward County Field Naturalists pay the costs of making its motion should the
Field Naturalist oppose it.

Undeterred, Wood says Gilead’s and MOE’s intimidation tactics have not stopped
her organization so far, nor are they likely to now.

Advertisements